The Lafayette Reservoir Tower Was Always Too Tall. This Fall It Finally Fits Its Dam

For close to a century, the tower in the Lafayette Reservoir stood about 40 feet taller than its job required. Most people on the rim saw a landmark. Dam engineers saw a height that matched a dam no one ever finished building.

This summer that mismatch was corrected. The roof and operating house came off, crews cut 13 concrete rings from the stem, and by late August the tower stood at its new height. The tower that walkers on the Lakeside Nature Trail see now is the version the reservoir's own dam called for in 1929.

A Tower Built for a Bigger Lake

The story starts with the dam. EBMUD's project page explains that when construction began in 1927, the plan was a dam 33 feet taller than the one in place today. That would have made a reservoir nearly three times larger. The dam is earth-filled, built from compacted layers of soil, and as it rose the soil could not carry that height. The embankment began to move, so the dam was built lower.

The outlet tower was already standing by then. It had gone up in 1929 to suit the larger dam, and it stayed that height for the next 97 years. The tower also does more than it appears to. It serves as the reservoir's spillway, and the California Division of Safety of Dams treats it as a critical structure. Seismic studies found that the extra height left it exposed in a large earthquake, so the state required EBMUD to retrofit it.

The state-approved fix corrects the 1920s mismatch directly. EBMUD's project summary reads, "EBMUD will shorten the tower by 40 feet to fit the height of the dam." The reservoir stays full, ratepayers fund the $14 million project, and the Division of Safety of Dams has approved it.

Lafayette Pushed to Keep the Height

The town did not accept the shorter tower quietly. As Lamorinda Weekly reported in August, the 100-year-old tower has long stood as a symbol of a city that incorporated in 1968, and the retrofit followed years of planning and resident objections at public meetings.

The City formed a Citizen Advisory Committee, and according to the City of Lafayette's tower design page, resident experts on that committee argued for keeping the full height. One of their proposals was to reinforce the upper half with mild steel, and the Council accepted the committee's recommendations.

By EBMUD's account, it held the project back more than a year and spent more than $500,000 reviewing the committee's concepts. Over three decades of study it had also developed at least three of its own designs that kept the full height. None was approved. In a November 2024 letter, the Division of Safety of Dams wrote that because the tower is both outlet and spillway, "any innovative remediation proposed must have a dam-specific record of proven performance."

What the community did win was the look of the top. When EBMUD presented three design options to the Council in 2017, then-Mayor Anderson favored the shorter version with lightweight design elements to keep the tower's familiar appearance. EBMUD says it built that feedback into a replacement operating house that resembles the original.

What Came Off, and What Goes Back On

Work on the tower itself followed a clear order this year. Here is where each piece stands as of early November, based on EBMUD's schedule and its monthly reports:

Phase Timing Status
Construction begins March 2026 Done
Roof and original operating house removed Early summer 2026 Done
13 concrete rings cut from the stem, about 40 feet in all Through about Aug. 21, 2026 Tower at its new height
Cast-in-place corbels to support the operating platform Inspected September 2026 State dam-safety inspection, no significant concerns noted
New metal operating house Targeted by November 2026 Fabrication began in August
Underwater slide gates, electric motor operators, testing Spring 2027 work window Scheduled
Overall project completion Fall 2027 on EBMUD's project page; March 2028 in a September report to EBMUD's board Ongoing

The cutting itself was methodical. Lamorinda Weekly described cranes and a barge lifting off the roof and operating house before crews saw-cut rings roughly 3 feet tall from the top of the stem. Bay Area Telegraph reported that EBMUD's Aug. 17 update had 10 of the 13 rings removed and the last three due by Aug. 21.

The new cap needs new supports underneath it. Before the operating house can go up, crews have to build a new floor within the remaining stem and add new corbels, which are the structural supports for the building above. EBMUD's September report to its board says state dam-safety inspectors reviewed the reinforcement and forms for those cast-in-place corbels and noted no significant concerns. EBMUD describes the replacement as a metal operating house that "closely resembles the existing 100-year-old design."

Work on the tower continues into 2027. When the seasonal environmental work window closes this fall, some work pauses. Crews return in spring 2027 to install underwater slide gates and electric motor operators, followed by electrical work, testing and commissioning before the tower returns to full service.

The Old Concrete May Stay in Town

Those 13 rings may not disappear entirely. Community members asked EBMUD to keep pieces of the original tower, and the utility has looked into making salvaged material into a historic token for the public. In September, EBMUD staff met with Councilmembers John McCormick and Jim Cervantes and City Manager Niroop Srivatsa about a commemorative display for the tower, covering its scope, budget and timeline. A follow-up meeting on Sept. 18 was held to finalize the discussion, and staff will keep working with those city representatives on the details of the final display.

Wildlife was part of the planning too. EBMUD put netting on the tower to keep birds from nesting during construction, and it said at a public meeting in February that the swallows that come back to the tower each year will be able to return when the work is done.

Walking the Reservoir This Winter

The recreation area has stayed open throughout. It draws more than a million visitors a year, and Lamorinda Weekly reported that tower work runs on weekdays only, which keeps weekend disruption low. Construction trucks use only the stretch of Mt. Diablo Boulevard to and from the Acalanes Road exit on Highway 24, so they stay out of downtown Lafayette. The City's Oct. 30 roundup still listed EBMUD's reservoir construction as ongoing.

A few practical notes before a cold-season loop:

  • Weekday delays. EBMUD's construction guidance, posted by the Lafayette Chamber of Commerce, says no vehicle closures are planned. Flaggers may work the park entrance and the paved Lakeside Nature Trail as needed, with occasional delays of 10 to 15 minutes.
  • Parking. EBMUD's 2026 fee schedule lists daily entry and parking for a car, motorcycle or small van at $7.
  • Hours. EBMUD's printed hours schedule lists November park hours of 6:30 a.m. to 5:30 p.m. once daylight saving time ends. Hours shift through the season, so check the reservoir page before an early-evening walk.
  • Fishing. EBMUD plants trout from November through March and posts its 2026–27 planting schedule on the reservoir page.
  • Boats. Rowboat and pedal-boat rentals are first come, first served.
  • Other work. A separate EBMUD wastewater collection project in the recreation area has been scheduled to run through fall 2026, so construction noise near the barge ramp and trail may come from more than one job.

EBMUD sends updates through its construction alert subscriptions, the quickest way to hear when the operating house goes up. For more on the town around the water, our Lafayette neighborhood page and our look at the newly filled corner of downtown Lafayette pick up where the rim trail ends.

At The Knapp Team, we follow Lafayette's landmarks through every change, including the tower that has finally been brought down to fit its own dam. If you live within sight of the reservoir and want to know how this year's changes in town relate to your home's value, request a free home valuation and we'll go through it with you.

Work With Us

With deep local expertise and strong market knowledge, The Knapp Team takes a strategic, client-focused approach to every real estate transaction. They understand each client’s goals and navigate the market with confidence and precision, delivering a smooth experience and exceptional results every time.

Follow Me on Instagram